2018-03-19 | Global Expo - progress of work

The modification of the FSO hall and office building has been proceeding according to the schedule. Currently works strengthening the existing foundation are being carried out as well as repair works in the steel hall construction. Moreover, the mounting of the media channels in this area has been initiated, and the process of bricklaying within the mezzanine and storage facilities has been  proceeding. The office building has been equipped with a roof covering and around 60% of work within the new facade and the window frames has been completed. The construction of the lift shaft in the restaurant area has been moving forward and the structure and the floors have been strengthened in the entrance zone to the office building.