2018-08-27 | Global Expo - news from construction site

Construction of Fair and Congress Center - the Global Expo continues. Nearly 99% of BSO system elevation works located in the office building are finished. The roof was made together with flashing. Glass windows have been installed on the ground floor and electrical installations are carried out. Because the conference and event hall will occupy an area of ​​2000 m2 with the option of dividing into 3 rooms: 870 m2, 565 m2, 580 m2, sliding walls were mounted.

About 80% of the floor works have been done on the high hall. Media channels are dug out, and the front is prepared for further pouring of the floor. Frames for sanitary equipment have been installed, and tiles and gres tiles are laid in the sanitary rooms. In addition, steel substructures for advertising on the eastern and southern elevations as well as substructures with guides for mobile walls are already finished.