2017-04-26 | MIASTECZKO WAWER- report from the site

Sanitary and electrical installation in garage is ongoing, walls in storage rooms and technical rooms are being assembled. Brickworks of inner and outer walls are being carried out on the first and the second floor of a new and converted part of the building. The ferroconcrete additional storeys of the third floor are nearing completion. The works on rain water sewer system are ongoing. The construction of the drive-in ramp has been started.