2016-11-24 | Diehl Namysłów – news from the site

Stage A

Construction works: hall sandwich panels  lining of the hall is terminated. Lean concrete was poured under the flor all over A Stage. Casting of floor in main hall is ongoing. Roof is already covered with metal sheets. Rockwool and membrane are being placed. Windows and indoor stairs assembly works are under development, smoke dampers and skylights are on their places.
Plumbing and sanitary works: household use water networks are carried out on the green area in front of the facility, installation of central heating, plumbing systems and pipelines in social part are on.  
Electric works: relocation of existing power supply , laying of concealed installations in social part,  wiring ducts assembly.
Road works: laying  curbs and ankles on the permanent use road (80% done).

Stage B

Construction works:  lean concrete was poured in the main hall, assembly works on the roof (membrane, Rockwool and metal sheets) are ongoing. Internal walls masonry works on level 1 are under development. Assembly of windows sub-constructions and sandwich panels are underway.  Staircases works status: masonry, stairs reinforcement of stairs concerting in progress, replacement of fire insulated wall panels – almost done (approx. 90% of works completed).   Plastering works in plantrooms in progress.
Plumbing and sanitary works: assembly of hydrant system pipes on upper storey, compressed air and sprinkler systems, nitrogen plants and vacuum installations on  the ground floor are ongoing.
Smoke removal system with smoke dampers – work in progress.
Mezzanine: drainage step-in, storm water system, roof piping works are being finished
Electric works: cable trays assembly on upper floor is  ongoing installation of an in-wall system has been initiated.