2019-12-16 | News from the construction site of the Miasteczko Wawer

We are pleased to inform you that the second stage of the Miasteczko Wawer investment is in progress. Works currently taking place include:
 
  • Bricklaying of TAB internal walls (floor +6, staircase “B")
  • Masonry partition walls from blocks of the Multigips type (storey +6, +7 - staircase "B"
  • Continuation of mineral wool thermal insulation installation in public areas: staircases, garage +1
  • Continuation of sanitary installation works
  • Continued installation of domestic ventilation
  • Installation of the internal electrical installation in residential premises on floors +5, +6, +7 (staircases "A" and "B")
  • Continuation of cosmetic and bottom plate repair works
  • Installation of window frames for eastern and western facades (floor +8)
  • Plastering walls (storey +1, +5 in staircase "A" and storey +1, +4 in staircase "B")
  • Continuation of facade works (southern and eastern facade of the staircase "B")
  • Commencement of facade works (west facade)
  • Continuation of works on the fire protection tank
  • Continuation of works in the field of external rainwater and sanitary installations, sewage, water and sewage connections
  • Cosmetic works of reinforced concrete structure
  • Installation of steel structure cladding made of T55 trapezoidal metal sheet in the technological holes in the ceiling above the +8 floor (at floor level +9)
  • Continuation of the roof waterproofing installation
  • Continuation of waterproofing the patio and terrace from the west
  • Preparation of elevator shafts in accordance with KONE requirements (painting)
  • Beginning of central heating installation works. in residential premises